2012 – Construction of a 6 level very high quality apartment complex with 2 levels of Carparking in the Basement levels for Stratum Management.
Wallace has been involved in construction of this high quality apartment complex in this difficult to build on site. The Basement levels have been constructed right to the boundary against established buildings. Wallace produced the tall Pre-cast wall panels and erected them on site while only excavating small areas of the bank with the use of No-fines concrete as backfill allowing waterproof tanking to be installed in a controlled condition. Due to the amount of ground work involved the building was staged in 2 sections then caught up once nearing completion of the final floors.