2015 – Wallace Building Contractors was contracted by Naylor Love to undertake the Concrete, Reinforcing and Comflor Installation to the Hutt City Council’s administration building in Laings Road which undertook a major seismic strengthening refurbishment and extension.
The building was extended with a new 4 story Annex constructed on the side of the existing building clad in glass and featuring a full height atrium. The Existing building had all foundations replaced with large foundation beams on piles with seismic upgrading of the exterior walls. All existing concrete floors were removed and replaced with a Comflor 80 flooring system with through deck welding installed by Wallace Buildings specialist company Wellington Stud Welding.