Republic 1 & 2

Republic 1 & 2

2010 – This 138 apartment building was built in 2 stages with a building footprint of 2400m2 and 3 levels of carparking for Stratum Management.

The buildings were constructed with large concrete shearwalls and the Stahlton flooring system. Once construction of Republic 1 was underway Wallace discussed with Stratum the possibility of starting work earlier than planned on the mainly carpark structure in the south tower of Republic 2.

The developers were keen to see the project advance and it meant the code of compliance issues arising from an unfinished carpark for Republic 1 was negated and the settlement date for purchasers on the first tower was brought forward two months, with completion of Republic 2 also earlier with handover ready at the end of June 2011.